Upgrading of Filtration Plant

Coteau-du-Lac, Quebec

completeDrinking WaterCC
Federal contribution
$712,500
Federal share25%

of $2.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 24, 2009
2010
Built

Approved 3 months before the announcement.

Program
Building Canada Fund - Communities Component
Ultimate recipient
City of Coteau-Du-Lac
Construction start
May 28, 2009(actual)
Construction end
Sep 14, 2010(actual)

Against the original forecast

  • Construction start3 months earlyforecast Sep 1, 2009
  • Construction end3 months earlyforecast Nov 30, 2010

Also in Coteau-du-Lac

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 28273 in the federal list. How to read these figures.