Renovation of the wastewater treatment plant
Federal contribution
$873,548
Federal share41%
of $2.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 7, 2017
201820192020
Built
Approved 7 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Régie d'assainissement des Coteaux
- Construction start
- May 22, 2018(actual)
- Construction end
- Feb 12, 2020(actual)
Against the original forecast
- Construction start5 weeks lateforecast Apr 15, 2018
- Construction end7 weeks earlyforecast Mar 31, 2020
Also in Coteau-du-Lac
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48904 in the federal list. How to read these figures.