Water and Drainage Pipe Construction

Warwick, Quebec

completeDrinking WaterCC
Federal contribution
$453,406
Federal share31%

of $1.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 10, 2009
2010
Built

Approved 2 months before the announcement.

Program
Building Canada Fund - Communities Component
Ultimate recipient
Town of Warwick
Construction start
Jun 3, 2009(actual)
Construction end
Oct 29, 2010(actual)

Against the original forecast

  • Construction end10 months lateforecast Dec 30, 2009