Renewal of water pipes
Federal contribution
$1.0M
$1,041,875
Federal share50%
of $2.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 20, 2017
20172018
Built
Approved 3 months before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Warwick
- Construction start
- Aug 7, 2017(actual)
- Construction end
- Sep 30, 2018(actual)
Against the original forecast
- Construction start16 months lateforecast Apr 1, 2016
- Construction end6 months earlyforecast Mar 31, 2019