Back to projects

Idylwyld Drive/8th Street Exit Ramp Overpass

Saskatoon, Saskatchewan

completeHighways and RoadsISF
Federal contribution
$395,500
Federal share33%

of $1.2M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMay 26, 2009
ApprovedJan 27, 2010
2010
Built

Approved 8 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Saskatoon
Construction start
Jun 2, 2010(actual)
Construction end
Nov 3, 2010(actual)

Against the original forecast

  • Construction start2 months lateforecast Apr 1, 2010

Also in Saskatoon

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 28367 in the federal list. How to read these figures.