Arterial Road Preservation - 8th Street
Federal contribution
$352,422
Federal share28%
of $1.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 5, 2009
2010
Built
Approved 3 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Saskatoon
- Construction start
- Sep 14, 2009(actual)
- Construction end
- Oct 13, 2010(actual)
Against the original forecast
- Construction end2 weeks earlyforecast Oct 30, 2010
Also in Saskatoon
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 28369 in the federal list. How to read these figures.