Sidewalk Replacement - Russell Road
Federal contribution
$41,493
Federal share32%
of $128.7K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMay 26, 2009
ApprovedJan 27, 2010
2010
Built
Approved 8 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Saskatoon
- Construction start
- Aug 18, 2010(actual)
- Construction end
- Sep 15, 2010(actual)
Against the original forecast
- Construction start7 weeks lateforecast Jun 30, 2010
Also in Saskatoon
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 28377 in the federal list. How to read these figures.