Street Rehabilitation - Kenderdine Road

Saskatoon, Saskatchewan

completeHighways and RoadsISF
Federal contribution
$249,200
Federal share33%

of $747.6K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMay 26, 2009
ApprovedJan 27, 2010
2010
Built

Approved 8 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Saskatoon
Construction start
Sep 7, 2009(actual)
Construction end
Oct 31, 2010(actual)

Against the original forecast

  • Construction end2 weeks lateforecast Oct 15, 2010

Also in Saskatoon

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 28380 in the federal list. How to read these figures.