Street Rehabilitation - Marquis Drive

Saskatoon, Saskatchewan

completeHighways and RoadsISF
Federal contribution
$135,000
Federal share33%

of $405.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMay 26, 2009
ApprovedJan 27, 2010
2010
Built

Approved 8 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Saskatoon
Construction start
May 27, 2009(actual)
Construction end
Jun 6, 2009(actual)

Against the original forecast

  • Construction end4 months earlyforecast Sep 30, 2009