Street Rehabilitation - Buena Vista Neighbourhood

Saskatoon, Saskatchewan

completeHighways and RoadsISF
Federal contribution
$154,500
Federal share33%

of $463.5K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedSep 24, 2009
ApprovedJan 27, 2010
20102011
Built

Approved 4 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Saskatoon
Construction start
Sep 15, 2010(actual)
Construction end
Aug 30, 2011(actual)