Back to projects

Renewel of Water Distribution and Watermain

Saskatoon, Saskatchewan

completeDrinking WaterISF
Federal contribution
$3.0M
$3,033,333
Federal share33%

of $9.1M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMay 26, 2009
ApprovedJan 27, 2010
2010
Built

Approved 8 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Saskatoon
Construction start
Jun 8, 2009(actual)
Construction end
Nov 23, 2010(actual)

Against the original forecast

  • Construction start12 months earlyforecast May 25, 2010
  • Construction end4 months earlyforecast Mar 31, 2011

Also in Saskatoon

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 28418 in the federal list. How to read these figures.