Ross Avenue Widening and Rehabilitation
Federal contribution
$958,599
Federal share29%
of $3.3M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMay 26, 2009
ApprovedJan 27, 2010
2010
Built
Approved 8 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Regina
- Construction start
- Sep 15, 2009(actual)
- Construction end
- Nov 4, 2010(actual)
Against the original forecast
- Construction end8 weeks lateforecast Sep 8, 2010
Also in Regina