Rehabilitaiton of 12th Avenue

Regina, Saskatchewan

completeHighways and RoadsISF
Federal contribution
$129,950
Federal share33%

of $389.9K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMay 26, 2009
ApprovedJan 27, 2010
2010
Built

Approved 8 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Regina
Construction start
Jun 15, 2009(actual)
Construction end
Jun 26, 2009(actual)

Against the original forecast

  • Construction start2 weeks lateforecast May 31, 2009
  • Construction end4 months earlyforecast Oct 31, 2009