Construction of a Pump Station - Global Transportation Hub
Federal contribution
$2.0M
$1,982,016
Federal share29%
of $6.9M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMay 26, 2009
ApprovedJan 27, 2010
20102011
Built
Approved 8 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Regina
- Construction start
- Aug 18, 2009(actual)
- Construction end
- Mar 31, 2011(actual)
Against the original forecast
- Construction start6 weeks earlyforecast Sep 30, 2009