Widening of Highway 2 Interchange Structure

Calgary, Alberta

completeHighways and RoadsISF
Federal contribution
$1.9M
$1,860,119
Federal share47%

of $3.9M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 2, 2009
ApprovedJul 23, 2010
20102011
Built

Approved 14 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Alberta
Construction start
Oct 1, 2009(actual)
Construction end
Nov 15, 2011(actual)

Against the original forecast

  • Construction end4 weeks lateforecast Oct 15, 2011

Also in Calgary

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 28482 in the federal list. How to read these figures.