Widening of Deerfoot Trail

Calgary, Alberta

completeHighways and RoadsISF
Federal contribution
$3.3M
$3,341,791
Federal share50%

of $6.7M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 2, 2009
ApprovedJul 23, 2010
20102011
Built

Approved 14 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Alberta
Construction start
Aug 24, 2009(actual)
Construction end
Feb 16, 2011(actual)

Against the original forecast

  • Construction start8 weeks lateforecast Jun 30, 2009
  • Construction end6 weeks earlyforecast Mar 31, 2011

Also in Calgary

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 28485 in the federal list. How to read these figures.