Federal contribution
$3.9M
$3,868,652
Federal share36%
of $10.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 31, 2009
201020112012
Built
Approved 2 months before the announcement.
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Parish of Saint-Michel
- Construction start
- Apr 1, 2011(actual)
- Construction end
- Mar 31, 2012(actual)