Schedule
Announced and approvedJun 28, 2018
20192020
Built
Approved 8 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Municipality of Saint-Michel
- Construction start
- Jan 14, 2019(actual)
- Construction end
- Mar 24, 2020(actual)
Against the original forecast
- Construction start4 months earlyforecast May 1, 2019
- Construction end8 weeks lateforecast Jan 31, 2020