Water and sewage infrastructure upgrades on Principale Street East
Federal contribution
$164,418
Federal share33%
of $493.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 28, 2009
2010
Built
Approved 3 months before the announcement.
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- City of Farnham
- Construction start
- Jun 16, 2009(actual)
- Construction end
- Dec 31, 2009(actual)
Against the original forecast
- Construction start2 weeks lateforecast Jun 1, 2009
- Construction end6 months earlyforecast Jul 15, 2010