Revitalization of Conrad-Blain Linear Park

Farnham, Quebec

completeRecreationCC Top Up
Federal contribution
$127,908
Federal share33%

of $383.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 12, 2010
2011
Built

Approved 6 weeks before the announcement.

Program
Building Canada Fund - Communities Component Top Up
Ultimate recipient
City of Farnham
Construction start
Oct 15, 2010(actual)
Construction end
Jun 30, 2011(actual)

Against the original forecast

  • Construction start7 months lateforecast Mar 1, 2010

Also in Farnham

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39583 in the federal list. How to read these figures.