Back to projects

Musée national des beaux-arts, Quebec City

Québec, Quebec

completeCultureMIC
Federal contribution
$33.7M
$33,700,000
Federal share47%

of $72.1M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedDec 21, 2007
ApprovedMay 28, 2009
20082010201220142016
Built

Approved 17 months after the announcement.

Program
Building Canada Fund - Major Infrastructure Component
Construction start
Jul 4, 2013(actual)
Construction end
Jul 31, 2016(actual)

Against the original forecast

  • Construction start2 months lateforecast Apr 30, 2013
  • Construction end5 weeks lateforecast Jun 24, 2016

Also in Québec

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 28633 in the federal list. How to read these figures.