Resurfacing Highway 43

Lac Ste. Anne County, Alberta

completeHighways and RoadsISF
Federal contribution
$939,522
Federal share50%

of $1.9M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJul 9, 2009
ApprovedJul 23, 2010
20102011
Built

Approved 12 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Alberta
Construction start
Aug 15, 2010(actual)
Construction end
Jan 17, 2011(actual)

Against the original forecast

  • Construction start3 months lateforecast May 1, 2010
  • Construction end2 months earlyforecast Mar 31, 2011