Back to projects

Darwell Lagoon Commission - Regional Wastewater Transmission Line - Phase B (Darwell to Trivillage)

Lac Ste. Anne County, Alberta

underwayWastewaterGIS
Federal contribution
$4.7M
$4,720,000
Federal share40%

of $11.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 25, 2020
today
2021202320252027
BuiltForecast

Approved 3 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Darwell Lagoon Commission
Construction start
Feb 1, 2023(actual)
Construction end
Aug 31, 2027(forecast)

Against the original forecast

  • Construction start2.5 years lateforecast Aug 15, 2020

Also in Lac Ste. Anne County

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56677 in the federal list. How to read these figures.