Resurfacing Highway 24
Federal contribution
$2.0M
$2,003,417
Federal share50%
of $4.0M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJul 9, 2009
ApprovedJul 23, 2010
20102011
Built
Approved 12 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Alberta
- Construction start
- Aug 1, 2010(actual)
- Construction end
- Jun 7, 2011(actual)
Against the original forecast
- Construction start3 months lateforecast May 1, 2010
- Construction end2 months lateforecast Mar 31, 2011
Also in Wheatland County
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 28687 in the federal list. How to read these figures.