Rehabilitation of Highway 21

Wheatland County, Alberta

completeHighways and RoadsISF
Federal contribution
$871,000
Federal share50%

of $1.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 29, 2010
Built

Approved 2 months before the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Alberta
Construction start
Aug 27, 2010(actual)
Construction end
Dec 15, 2010(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Aug 3, 2010
  • Construction end3 months earlyforecast Mar 31, 2011