Resurfacing Highway 22
Federal contribution
$1.4M
$1,375,026
Federal share50%
of $2.8M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJul 9, 2009
ApprovedJul 23, 2010
2010
Built
Approved 12 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Alberta
- Construction start
- Sep 8, 2009(actual)
- Construction end
- Nov 25, 2009(actual)
Against the original forecast
- Construction start8 months earlyforecast May 15, 2010
- Construction end7 months earlyforecast Jun 30, 2010
Also in Cochrane
- Centre Avenue Complete Street Connector$3.0M
- Resurfacing Highway 1A$795.7K
- Existing multi-use pathway paving upgrades and wayfinding in Cochrane, Alberta$770.4K
- Policy development of multi-modal traffic bylaw with pathway and wayfinding design standards in Cochrane, Alberta$50.0K
- The Trail / Completing the Trail from Calgary to Canmore (2 stages) - A Project by The Rotary Club of Cochrane$50.0K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 28688 in the federal list. How to read these figures.