Existing multi-use pathway paving upgrades and wayfinding in Cochrane, Alberta
Federal contribution
$770,400
Federal share60%
of $1.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 26, 2024
today
202320242025202620272028
BuiltForecast
Approved 18 months before the announcement.
- Program
- Active Transportation Fund
- Ultimate recipient
- Town of Cochrane
- Construction start
- May 31, 2023(actual)
- Construction end
- Nov 30, 2027(forecast)
Also in Cochrane
- Centre Avenue Complete Street Connector$3.0M
- Resurfacing Highway 22$1.4M
- Resurfacing Highway 1A$795.7K
- Policy development of multi-modal traffic bylaw with pathway and wayfinding design standards in Cochrane, Alberta$50.0K
- The Trail / Completing the Trail from Calgary to Canmore (2 stages) - A Project by The Rotary Club of Cochrane$50.0K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 64229 in the federal list. How to read these figures.