Resurfacing Highway 1A

Canmore, Alberta

completeHighways and RoadsISF
Federal contribution
$789,507
Federal share48%

of $1.6M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJul 9, 2009
ApprovedJul 23, 2010
2010
Built

Approved 12 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Alberta
Construction start
Sep 8, 2009(actual)
Construction end
Nov 15, 2009(actual)

Against the original forecast

  • Construction start8 months earlyforecast May 15, 2010
  • Construction end16 months earlyforecast Mar 31, 2011