Resurfacing Highway 1A
Federal contribution
$789,507
Federal share48%
of $1.6M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJul 9, 2009
ApprovedJul 23, 2010
2010
Built
Approved 12 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Alberta
- Construction start
- Sep 8, 2009(actual)
- Construction end
- Nov 15, 2009(actual)
Against the original forecast
- Construction start8 months earlyforecast May 15, 2010
- Construction end16 months earlyforecast Mar 31, 2011
Also in Canmore
- Cougar Creek Long Term Flood Mitigation$13.0M
- Purchase of vehicles and supporting infrastructure to expand public transit capacity for the residents of Stoney Nakoda Nation in Alberta$2.3M
- Highway 1 - Rehabilitation East of Banff Park, East of the Kananaskis River$1.7M
- Bow Valley Trail Transit Connectivity$1.6M
- Resurfacing Highway 1$1.5M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 28692 in the federal list. How to read these figures.