Resurfacing Highway 17

Lloydminster, Alberta

completeHighways and RoadsISF
Federal contribution
$1.5M
$1,471,571
Federal share49%

of $3.0M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJul 9, 2009
ApprovedJul 23, 2010
2010
Built

Approved 12 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Alberta
Construction start
Feb 17, 2010(actual)
Construction end
Oct 31, 2010(actual)

Against the original forecast

  • Construction start2 months earlyforecast May 1, 2010
  • Construction end5 months earlyforecast Mar 31, 2011

Also in Lloydminster