Lloydminster New Mechanical Wastewater Treatment Facility
Federal contribution
$9.1M
$9,078,915
Federal share13%
of $72.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 27, 2019
201920202021202220232024
Built
Approved 4 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- City of Lloydminster
- Construction start
- Nov 15, 2020(actual)
- Construction end
- Nov 13, 2023(actual)
Against the original forecast
- Construction end7 weeks earlyforecast Dec 31, 2023
Also in Lloydminster
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 53116 in the federal list. How to read these figures.