Resurfacing Highway 13

Killam, Alberta

completeHighways and RoadsISF
Federal contribution
$1.4M
$1,357,789
Federal share50%

of $2.7M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJul 9, 2009
ApprovedJul 23, 2010
2010
Built

Approved 12 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Alberta
Construction start
May 15, 2010(actual)
Construction end
Aug 11, 2010(actual)

Against the original forecast

  • Construction start2 weeks lateforecast May 1, 2010
  • Construction end8 months earlyforecast Mar 31, 2011

Also in Killam

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 28702 in the federal list. How to read these figures.