Resurfacing Highway 36
Federal contribution
$4.7M
$4,677,203
Federal share50%
of $9.4M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJul 9, 2009
ApprovedJul 23, 2010
2010
Built
Approved 12 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Alberta
- Construction start
- May 15, 2010(actual)
- Construction end
- Aug 30, 2010(actual)
Against the original forecast
- Construction start2 weeks lateforecast May 1, 2010
- Construction end7 months earlyforecast Mar 31, 2011
Also in Killam
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 28703 in the federal list. How to read these figures.