Modernize drinking water supplay system and bring it up to date
Federal contribution
$152,139
Federal share25%
of $608.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 2, 2009
2010
Built
Approved 3 months before the announcement.
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Municipality of Girardville
- Construction start
- Mar 1, 2010(actual)
- Construction end
- Oct 15, 2010(actual)
Against the original forecast
- Construction start5 weeks earlyforecast Apr 5, 2010
Also in Girardville