Back to projects

Modernization of the drinking water treatment plant and wastewater phosphate removal equipment

Girardville, Quebec

completeDrinking WaterCWWF
Federal contribution
$425,693
Federal share50%

of $851.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 26, 2017
20172018
Built

Approved 5 months before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Municipality of Girardville
Construction start
Aug 1, 2017(actual)
Construction end
Sep 7, 2018(actual)

Against the original forecast

  • Construction start3 months lateforecast May 1, 2017
  • Construction end7 months earlyforecast Mar 31, 2019

Also in Girardville