Wastewater treatment in Center area
Federal contribution
$1.2M
$1,224,183
Federal share37%
of $3.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 30, 2009
2010201220142016
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Municipality of Chelsea
- Construction start
- Nov 16, 2011(actual)
- Construction end
- Dec 20, 2016(actual)
Against the original forecast
- Construction start2.7 years earlyforecast Aug 1, 2014
- Construction end18 months lateforecast Jun 30, 2015
Also in Chelsea
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 28708 in the federal list. How to read these figures.