Development of a bike path
Federal contribution
$487,415
Federal share33%
of $1.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 29, 2018
20162018202020222024
Built
Approved 10 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Municipality of Chelsea
- Construction start
- Jan 1, 2016(actual)
- Construction end
- May 30, 2024(actual)
Against the original forecast
- Construction start3.5 years earlyforecast Jun 15, 2019
- Construction end4.5 years lateforecast Nov 30, 2019
Also in Chelsea
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50138 in the federal list. How to read these figures.