Back to projects

Development of a bike path

Chelsea, Quebec

completeActive TransportationSCF
Federal contribution
$487,415
Federal share33%

of $1.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 29, 2018
20162018202020222024
Built

Approved 10 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Municipality of Chelsea
Construction start
Jan 1, 2016(actual)
Construction end
May 30, 2024(actual)

Against the original forecast

  • Construction start3.5 years earlyforecast Jun 15, 2019
  • Construction end4.5 years lateforecast Nov 30, 2019

Also in Chelsea

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50138 in the federal list. How to read these figures.