Resurfacing of Elevator Road and Cargill Road
Federal contribution
$334,682
Federal share33%
of $1.0M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJul 9, 2009
ApprovedJul 23, 2010
2010
Built
Approved 12 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Municipal District of Spirit River
- Construction start
- Oct 12, 2009(actual)
- Construction end
- May 25, 2010(actual)
Against the original forecast
- Construction start7 months earlyforecast May 1, 2010
- Construction end5 months earlyforecast Oct 30, 2010
Also in Spirit River
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 28767 in the federal list. How to read these figures.