Main Street Storm Sewer

Spirit River, Alberta

completeWastewaterISF
Federal contribution
$235,571
Federal share29%

of $802.1K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJul 9, 2009
ApprovedJul 23, 2010
2010
Built

Approved 12 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Town of Spirit River
Construction start
Jun 28, 2010(actual)
Construction end
Sep 30, 2010(actual)

Against the original forecast

  • Construction end3 months earlyforecast Dec 31, 2010