Sewage Lagoon Upgrade
Federal contribution
$169,000
Federal share33%
of $507.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJul 9, 2009
ApprovedJul 23, 2010
20102011
Built
Approved 12 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Town of Fairview
- Construction start
- Jul 10, 2009(actual)
- Construction end
- Mar 8, 2011(actual)
Against the original forecast
- Construction end2 months lateforecast Dec 30, 2010
Also in Fairview
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 28864 in the federal list. How to read these figures.