Highway 682 - Hines Creek Bridge
Federal contribution
$160,500
Federal share50%
of $321.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJan 28, 2010
ApprovedJul 23, 2010
Built
Approved 6 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Alberta
- Construction start
- Jul 20, 2010(actual)
- Construction end
- Oct 7, 2010(actual)
Against the original forecast
- Construction start2 weeks lateforecast Jul 5, 2010
- Construction end6 months earlyforecast Mar 31, 2011
Also in Fairview
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39543 in the federal list. How to read these figures.