Reconstruction of 55th Avenue

High Prairie, Alberta

completeHighways and RoadsISF
Federal contribution
$521,264
Federal share21%

of $2.5M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJul 9, 2009
ApprovedJul 23, 2010
2010
Built

Approved 12 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Town of High Prairie
Construction start
Jun 4, 2010(actual)
Construction end
Oct 15, 2010(actual)

Against the original forecast

  • Construction start5 weeks lateforecast May 1, 2010
  • Construction end3 months earlyforecast Dec 31, 2010

Also in High Prairie

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 28887 in the federal list. How to read these figures.