Reconstruction of 56th Avenue

High Prairie, Alberta

completeHighways and RoadsISF
Federal contribution
$488,916
Federal share20%

of $2.5M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJul 9, 2009
ApprovedJul 23, 2010
2010
Built

Approved 12 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Town of High Prairie
Construction start
Jun 4, 2010(actual)
Construction end
Oct 15, 2010(actual)

Against the original forecast

  • Construction end5 months earlyforecast Mar 31, 2011