8th Street and Idlewyld Drive Primary Watermain Rehabilitation

Saskatoon, Saskatchewan

completeDrinking WaterISF
Federal contribution
$206,764
Federal share30%

of $700.1K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedSep 24, 2009
ApprovedJan 27, 2010
20102011
Built

Approved 4 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Saskatoon
Construction start
Oct 1, 2010(actual)
Construction end
May 31, 2011(actual)

Against the original forecast

  • Construction end6 months lateforecast Nov 30, 2010