Highway 97 - Stormy Road North

100 Mile House, British Columbia

completeHighways and RoadsISF
Federal contribution
$1.0M
$1,026,854
Federal share50%

of $2.1M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedApr 7, 2009
ApprovedJan 25, 2010
2010
Built

Approved 10 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Apr 14, 2009(actual)
Construction end
Oct 17, 2010(actual)

Against the original forecast

  • Construction start5 months earlyforecast Sep 21, 2009
  • Construction end12 months lateforecast Oct 30, 2009

Also in 100 Mile House

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 28966 in the federal list. How to read these figures.