100 Mile House - Horse Lake Road Bridge Replacement

100 Mile House, British Columbia

completeHighways and RoadsRNIS
Federal contribution
$1.0M
$1,048,800
Federal share60%

of $1.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 11, 2022
2022202320242025
Built

Approved 2 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Construction start
May 5, 2025(actual)
Construction end
Nov 5, 2025(actual)

Against the original forecast

  • Construction start4 weeks earlyforecast Jun 1, 2025
  • Construction end8 months earlyforecast Jun 30, 2026