Surrey Bicycle Network

Surrey, British Columbia

completeActive TransportationISF
Federal contribution
$3.5M
$3,508,948
Federal share33%

of $10.8M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedApr 7, 2009
ApprovedJan 25, 2010
20102011
Built

Approved 10 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Surrey
Construction start
Sep 1, 2009(actual)
Construction end
Oct 22, 2011(actual)

Against the original forecast

  • Construction start3 months lateforecast Jun 1, 2009