Construction of the City Centre Library

Surrey, British Columbia

completeCultureISF
Federal contribution
$10.0M
$10,000,000
Federal share28%

of $36.0M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedSep 24, 2009
ApprovedJan 25, 2010
20102011
Built

Approved 4 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Surrey
Construction start
Mar 5, 2010(actual)
Construction end
Aug 31, 2011(actual)

Against the original forecast

  • Construction end4 weeks lateforecast Jul 31, 2011