Surrey Museum Phase 2 Expansion

Surrey, British Columbia

completeCultureNRP
Federal contribution
$4.5M
$4,464,575
Federal share30%

of $15.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 27, 2017
201820192020
Built

Approved 4 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - National and Regional Projects
Ultimate recipient
City of Surrey
Construction start
Oct 2, 2017(actual)
Construction end
May 7, 2020(actual)

Against the original forecast

  • Construction start3 months lateforecast Jun 30, 2017
  • Construction end8 weeks earlyforecast Jun 30, 2020