Trunk 16 (from Trunk 4) - Major Collector Highway

Monastery, Nova Scotia

completeHighways and RoadsISF
Federal contribution
$606,596
Federal share48%

of $1.3M total eligible cost; the rest comes from other partners.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Nova Scotia
Construction start
Jul 17, 2009(actual)
Construction end
Jul 28, 2009(actual)

Against the original forecast

  • Construction start7 weeks lateforecast Jun 1, 2009
  • Construction end3 months earlyforecast Oct 31, 2009

Also in Monastery

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 28985 in the federal list. How to read these figures.