Rehabilitation of Highway 104 Overpasses
Federal contribution
$549,245
Federal share49%
of $1.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 13, 2009
20102011
Built
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Nova Scotia
- Construction start
- Jul 6, 2010(actual)
- Construction end
- May 30, 2011(actual)
Also in Monastery